How are Hyundai power transformers factory-tested and commissioned before integration into substation service cycles?
- 该话题包含 1个回复,2 人参与,最后由 更新于 1周、 2天前 。
Answers
-
一月 20, 2026 6:30 下午 by Eric King
Factory testing follows IEC/IEEE standards and includes routine tests (ratio, losses, resistance, impedance), insulation withstand tests, and sometimes temperature rise and PD tests. Commissioning on site includes oil sampling, grounding checks, OLTC verification, relay settings, SCADA integration, and thermal scanning before energization.