Power Transformer
What determines the cost of a power transformer in utility procurement?
- 该话题包含 1个回复,2 人参与,最后由 更新于 4天、 11小时前 。
Answers
-
一月 25, 2026 11:18 下午 by Plinio Leiva-Bou
Utility procurement considers capital cost, guaranteed losses, lifecycle energy cost, reliability history, and service support. Larger utilities may require competitive tenders with strict technical evaluations. Costs are affected by specialized requirements like high BIL, seismic performance, fire-safe designs, and advanced online monitoring. Factory testing, on-site commissioning, extended warranties, and spare units also factor in. Long lead times, transport complexity, and substation civil works often dwarf the bare equipment price.