What steps are involved in commissioning a power transformer?
- 该话题包含 1个回复,2 人参与,最后由 更新于 1周、 3天前 。
Answers
-
一月 19, 2026 11:28 下午 by 山田 英樹
Commissioning typically includes visual inspection, nameplate verification, oil level and moisture checks, ratio test, winding resistance test, insulation resistance, tan-delta, DGA baseline sampling, OLTC functional checks, bushing inspection, cooling system tests, relay and protection coordination, tap verification, vector group confirmation, and energization under controlled conditions. Load acceptance and thermal stability are confirmed before handover.