Inquiry for a vacuum transformer drying plant suitable for transformers rated 1000-5000 kVA, including process duration information for comparison with the current method.
- Este debate tiene 1 respuesta, 2 mensajes y ha sido actualizado por última vez el hace 1 mes por .
Answers
-
noviembre 9, 2025 a las 12:51 am by Ahmed Abdullah
GlobeCore vacuum drying plants are designed for transformers up to 5000 kVA. The process time depends on transformer size and insulation condition but typically ranges from 8 to 20 hours. We will provide a quotation and process details.