enero 27, 2026 a las 4:57 pm en respuesta a: How to calculate efficiency of power transformer? #332287Jessica MitchellMiembro
? = Output (kW) / Input (kW). Load and no-load losses derived from SC/OC tests.
Jessica MitchellMiembroTotal losses = No-load (core + dielectric) + Load losses (I²R + stray + eddy). Standards IEC/IEEE specify test-derived values using open-circuit/short-circuit tests and temperature correction. Losses are expressed in watts or kW at rated load for economic evaluation.
enero 26, 2026 a las 2:58 pm en respuesta a: Why is neutral grounding applied to a power transformer? #332071Jessica MitchellMiembroEnsures transient overvoltage control, enables single-line-to-ground fault detection, and reduces insulation stress.
enero 26, 2026 a las 12:55 pm en respuesta a: Why is a power transformer installed on a pole for distribution? #332044Jessica MitchellMiembroPole-mounted units reduce installation cost and provide LV service to neighborhoods. Elevation offers safety clearance and flood protection.
enero 25, 2026 a las 3:35 pm en respuesta a: What is the importance of transformers in an electrical power system? #331877Jessica MitchellMiembroTransformers enable voltage adaptation for efficient transmission and safe distribution. They provide isolation, allow protection coordination, support reactive power flow, and permit integration of generation, transmission, and distribution segments into a unified grid.
enero 24, 2026 a las 12:20 pm en respuesta a: Where can second hand power transformers for sale be purchased? #331665Jessica MitchellMiembroSecond-hand units are bought via refurbishers, utilities offloading old fleet, decommissioning contractors, and surplus marketplaces that provide test data.
enero 24, 2026 a las 8:59 am en respuesta a: How is the power rating of a transformer calculated in kVA? #331627Jessica MitchellMiembroS=VI for single-phase and S=?3VI for three-phase; ratings include thermal and impedance considerations.
enero 24, 2026 a las 5:54 am en respuesta a: How long does it take to replace a power transformer after failure? #331603Jessica MitchellMiembroReplacement depends on procurement lead time (months for large units), logistics, installation, oil processing, and commissioning; expedited replacements may still take weeks.
enero 23, 2026 a las 2:12 am en respuesta a: What certifications must a manufacturer of power transformers comply with for utility markets? #331373Jessica MitchellMiembroManufacturers must comply with international and regional standards such as IEC 60076 or IEEE/ANSI C57 series for design, testing, insulation coordination, and performance. They may need ISO 9001 for quality management, ISO 14001 for environmental management, and ISO 45001 for occupational health and safety. For specific markets, utilities require type-test reports, routine-test certificates, and sometimes third-party certifications or grid code compliance. Seismic, fire, and EMC standards may also apply depending on installation conditions and regulatory frameworks.
enero 22, 2026 a las 1:08 am en respuesta a: What does a power transformer testing PDF contain? #331102Jessica MitchellMiembroIt contains standardized test procedures, instrumentation requirements, acceptance criteria, and reporting templates for electrical, mechanical, and dielectric performance verification. Loss testing, impedance measurement, vector group checks, and oil diagnostics are usually included.
enero 21, 2026 a las 2:57 am en respuesta a: How do power transformers work in electrical power transmission? #330760Jessica MitchellMiembroGSUs raise generator output to transmission voltages to reduce line losses; power transformers in substations later step voltage down for distribution.
enero 20, 2026 a las 12:57 pm en respuesta a: How does a step down transformer alter voltage from a power line to a building? #330555Jessica MitchellMiembroDistribution transformers step line voltage (e.g., 11-33kV) down to service levels such as 230/400V or split-phase 120/240V for buildings.
enero 19, 2026 a las 5:40 pm en respuesta a: What steps are involved in power transformer assembly during manufacturing? #330380Jessica MitchellMiembroAssembly involves core stacking, clamping, coil winding, insulation layering, core-coil assembly, brazing or soldering connections, lead routing, OLTC integration, bushing installation, tank assembly, vacuum oil filling, leak testing, and factory routine tests per IEC/IEEE.
Jessica MitchellMiembroACTOM transformers are deployed across African utility networks, mining operations, industrial plants, and large commercial facilities. They serve MV/LV distribution, substation duty, and industrial feeders requiring robust mechanical short-circuit withstand.
noviembre 8, 2025 a las 5:31 pm en respuesta a: I need information about this machine CMM-6/7. Please send us a quotation for this equipment or another with the same conditions and quality. #327230Jessica MitchellMiembroThe CMM-6/7 is a transformer oil purification plant with approximately 6-7 m³/h capacity. It removes water, gases, and impurities under vacuum. We will prepare a quotation and suggest equivalent models with the same performance and quality.
noviembre 8, 2025 a las 9:38 am en respuesta a: I’d like you to send me an offer for one TOR-80 LS. Thanks. #327200Jessica MitchellMiembroThe TOR-80 LS is a semi-automatic breakdown-voltage tester rated up to 80 kV, compliant with IEC 60156. We will send a commercial offer with technical datasheet and lead time.
noviembre 7, 2025 a las 11:28 am en respuesta a: OIL MOISTURE METER TOR-1 Can this type measure the moisture in honey? Please quote the equipment price to us #327104Jessica MitchellMiembroThe TOR-1 is designed for measuring dissolved water in transformer and insulating oils. It is not calibrated for use with honey or food products. We can provide a quotation for the standard oil moisture measurement configuration.
noviembre 7, 2025 a las 8:50 am en respuesta a: Please can you give me a quote on CMM-G Wind Turbine Gearbox Oil Changer #327094Jessica MitchellMiembroThe CMM-G unit performs oil changing and filtration for wind turbine gearboxes. It includes heating, flow control, and filtration up to 3 microns. We will prepare a quotation and technical sheet.
Jessica MitchellMiembroThe TOR-1 moisture meter measures water content in transformer oil in ppm. It provides results within 10 minutes per sample. We will send a quotation including lead time and specifications.
septiembre 17, 2025 a las 7:55 am en respuesta a: What are essential transformer components and maintenance tips? #325533Jessica MitchellMiembroKey components include the core, windings, bushings, conservator, and oil system. Maintenance includes regular oil testing, filtration, thermal imaging, and tightening connections. GlobeCore provides full-cycle oil treatment systems that support preventive and predictive transformer maintenance.
-
AutorEntradas